PART 1
Project Scope
Project Objective
The project involves construction of a lake house project whereby assorted size rental units will be constructed on a 500*500 feet piece of land that is part of my investment for the project apart from the fronted investment fund. The rental units are projected to have a return of $5,000, $8,000 and $10,000. This project is supposed to provide a viable investment opportunity as a by providing executive housing solution to the growing population in Denver.
Project Deliverables
The project Deliverables include 6 mansionettes fully built with both standard interior and exterior features.
Milestones
Mobilization of onsite requirements installations
Laying of foundation
Concrete Forming and Pouring – Floors and Roof
Masonry work
Roofing
Installing finishes
Plumbing
Electrical
Heating and ventilating
Complete final Inspection
Technical Requirements
Electricals
Heating and ventilating equipment
Logistics
Project Constraints
Lack of enough time to complete milestones. Since the project works on estimated time, the project is exposed to the risk of falling behind schedule if one phase of the projects slacks.
Lack of enough capital. Since funding will mainly come from different stakeholders, reliance on them as a source of funding exposes the project to delays when a stakeholder fails behind in their payments.
. The project is a labour intensive project thus having reliable skilled and non-skilled workers will be paramount in making sure the project does not stall.
Ethical and Social Responsibility considerations
Reduction in carbon footprints through the use of solar energy and biogas as the main source of lighting and heating for the houses.
85% of supplies for the project, including labor and construction materials will mainly come from established manufacturers or suppliers from the Denver locality as a mode of benefiting the local environment.
The Lake housing will also prioritize the needs of local citizens concerning the project, for example effect of the project on social integration during the planning phase of the project.
Customer review
(Enter Instructors feedback)
PART 2
Formal Letter to the Instructor
Herbert Greene
Antietam Dr
Locust Grove, VA
(Dr. Cuffee), Designation
Dear Sir
I hereby write to provide a general overview of the Work Breakdown Structure for the Lake House Project (LHP). The project will mainly involve four resources including General contractor, Architect, Owner, & Mortgage lender. The project will start immediately after the finalization of plans and development of estimates among the management and external stakeholders. This will be followed by the application of necessary from authorities responsible in Denver including HVAC permit. The provision will be followed by the site work for preparation of the main construction site. This involves clearing and grubbing the unnecessary lot and installing ground and power service. Accomplishment of this step will be an important process in supporting establishment of the main foundation for the housing units including excavating and laying foundation for basement walls. This notion will be followed by framing and Dry In. The exterior walls finishing will be the next step which will be done concurrently with the plumbing and interior finishing. The last stage will involve landscaping and ground works which involves installing backyard fences and establishing concrete driveways and sidewalks. Finally, the project manager will evaluate and submit a final report on the project whereby the deliverables will be assessed for their quality.
Attached is a a visualization of the WBS including the critical paths for the project.
Yours sincerely
(Student Name), Project Manager
Gantt Chart
Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.
You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.
Read moreEach paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.
Read moreThanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.
Read moreYour email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.
Read moreBy sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.
Read more